Timeline
18 months
Budget
$128M
Location
Aswan, EG
Impact
1.4M TEU throughput
Overview
An equipment port and logistics terminal at Aswan with 1.4 million TEU annual throughput capacity. The facility combines berthing infrastructure, gantry crane systems, container yards, and inland connectivity — serving Upper Egypt's industrial and trade corridors.
Gallery


Technical Data
Annual Throughput
1.4M TEU
Berth Length
1,200 m
Gantry Cranes
12 units
Container Yard Area
85,000 m²
Reefer Points
1,800 plugs
Truck Gates
10 lanes
Rail Siding
2 km
On-Site Power
6 MW substation
Delivery Status
Completed
Hydrographic, traffic, and demand studies finalized.
Completed
Marine and landside engineering approved.
In Progress
Quay wall 70% complete; yard paving underway.
Upcoming
Target Q4 2026 — crane commissioning and trial operations.